Research and application of curtain forming and controlled grouting technology for overburden with pressurized flow water
-
摘要: 蓄水条件一定水头下的坝基覆盖层渗漏采用灌浆进行防渗处理时,面临水泥浆液抗动水冲释性差而被流水稀释分散、水流冲失以致灌浆难以成幕防渗以及耗浆量极大等难题。结合工程实践,本文研究了采用抗动水分散浆液、膏状浆液,遵循先堵后灌原则,上下游分排灌注不同浆液,解决了有压动水覆盖层防渗帷幕成幕及控制灌浆相关问题。工程应用效果好,为类似渗漏工程治理提供了重要的参考借鉴。Abstract: During the process of grouting for seepage treatment of dam foundation overburden under some water head when retaining water, problems such as slurry dispersing, incomplete curtain, large consumption of cement, may be encountered. In reference to field practice, this paper investigates the use of the anti-washout slurry and the paste-like slurry, the injection-after-sealing principle, and grouting in tiers of different types of slurry for the upstream and downstream to solve the technical problems related to grouting of the overburden anti-seepage curtain and control of grouting under pressurized flow water. The technology produced good field results and can provide important reference for similar seepage treatment.
-
-
[1] 姚志辉,黄艳莉.泸定水电站坝基高水头深厚覆盖层帷幕灌浆施工技术研究[J].水利水电技术,2013,41(5):1-3,9.
YAO Zhihui, HUANG Yanli. Study on construction technology of curtain grouting for deep overburden upon dam foundation under high head for Luding Hydropower Station[J]. Water Resources and Hydropower Engineering, 2013,41(5):1-3,9.
[2] [2] 李正顺.大渡河丹巴水电站坝基深厚覆盖层工程地质研究[D].成都:成都理工大学,2008.LI Zhengshun. Study on the engineering geological property of deep overburden in the Danba Hydroelectric Power Station[D]. Chengdu: Chengdu University of Technology, 2008.
[3] [3] 范峥,钟久安,何非凡,等.高聚物复合堵水浆材在岩溶地区深孔帷幕灌浆中的应用[J].探矿工程(岩土钻掘工程),2020,47(1):86-90.
FAN Zheng, ZHONG Jiuan, HE Feifan, et al. Application of high polymer composite water blocking slurry in deep hole curtain grouting in the karst area[J]. Exploration Engineering (Rock & Soil Drilling and Tunneling), 2020,47(1):86-90.
[4] [4] 黄庆豪,侍克斌,毛海涛,等.固结灌浆深度对丹巴水电站深厚覆盖层坝基中流固耦合的影响[J].水电能源科学,2020,38(5):86-90.
HUANG Qinghao, SHI Kebin, MAO Haitao, et al. Effect of consolidation grouting depth on fluid-solid coupling in deep overburden dam foundation of Danba Hydropower Station[J]. Water Resources and Power, 2020,38(5):86-90.
[5] [5] 张漆,巨彬.深孔覆盖层防渗灌浆试验在工程施工中的应用[J].水利建设与管理,2020,40(3):58-62,84.
ZHANG Qi, JU bin. Application of impervious grouting test of deep hole overburden layer in engineering construction[J]. Water Resources Development & Management, 2020,40(3):58-62,84.
[6] [6] 唐应鹏.斜卡电站深厚覆盖层水泥化学复合灌浆技术浅谈[J].四川水利,2015(5):79-80.
TANG Yingpeng. Discussion on cement chemical composite grouting technology for deep overburden of Xieka Hydropower Station[J]. Sichuan Water Conservancy, 2015(5):79-80.
[7] [7] 杨向东,朱红梅.国内聚氨酯灌浆材料的种类及其应用领域[J].山东工业技术,2015(2):140-141.
YANG Xiangdong, ZHU Hongmei. Types and application fields of polyurethane grouting materials in China[J]. Shandong Industrial Technology, 2015(2):140-141.
[8] [8] 骆秋林.桐子林水电站深厚覆盖层全帷幕灌浆技术[C]//
中国水利学会地基与基础工程专业委员会第13次全国学术会议论文集 ,2015:327-331.LUO Qiulin. Full curtain grouting technology for deep overburden of Tongzilin Hydropower Station[C]//
Proceedings of the 13th National Academic Conference of Foundation and Foundation Engineering Committee of China Hydraulic Society , 2015:327-331.[9] [9] 罗先进,何江达,谢红强,等.深覆盖层闸坝结构特性及基础处理措施研究[J].中国农村水利水电,2013(3):114-118,122.
LUO Xianjin, HE Jiangda, XIE Hongqiang, et al. Research on dam structure characteristics and foundation treatment measures for gate dams on deep overburden layers[J]. China Rural Water and Hydropower, 2013(3):114-118,122.
[10] [10]
[S].DL/T 5406—2010 ,水工建筑物化学灌浆施工规范 [S].DL/T 5406—2010 , Specification for chemical grouting construction of hydraulic structures[11] [11]
[S].DL/T 5267—2012 , 水电水利工程覆盖层灌浆技术规范 [S].DL/T 5267—2012 , Specification of overburden grouting for hydropower and water resources projects[12] [12] 张传虎,刘传炜,张红曾,等.深厚覆盖层围堰综合防渗体系施工关键技术[J].电力勘测设计,2018(12):41-45.
ZHANG Chuanhu, LIU Chuanwei, ZHANG Hongzeng, et al. Key technology for construction of deep overburden cofferdam with comprehensive anti-seepage system[J]. Electric Power Survey & Design, 2018(12):41-45.
[13] [13] 潘松林.谈浅覆盖层地段地表预加固灌浆施工[J].山西建筑,2016,42(7): 80-81.
PAN Songlin. Discussion on pre-reinforcement grouting construction of shallow overburden area surface[J]. Shanxi Architecture, 2016,42(7):80-81.
[14] [14] 李振学,李明辉.泸定水电站深厚覆盖层防渗墙施工技术[J].水力发电,2012,38(1):50-53.
LI Zhenxue, LI Minghui. Construction of cut-off wall in deep overburden for Luding Hydropower Station[J]. Water Power, 2012,38(1):50-53.
[15] [15] 胡小顺.覆盖层无盖重条件下灌浆施工工艺[J].科技传播,2010(20):111,103.HU Xiaoshun. Covering layer under the condition without coverheavy construction croft grouting[J]. Public Communication of Science & Technology, 2010(20):111,103.
-
计量
- 文章访问数: 1004
- PDF下载数: 96
- 施引文献: 0